|
WORLD'S
LARGEST FABRIC-FORMED COLUMN PADS
|
 |
|
Scott
Saunders double checks steel placement prior to pouring concrete |
The GIUSTI Group,
Calgary Alberta formed concrete
foundations, columns and floors for a six story
concrete and steel condominium project in
Kelowna, BC.
The Giusti Group began as a custom
home builder in 1973, by 1986 were building
multi-family complexes. The Company has now built more than 600
custom homes and 35,000 multi-family units.
The 285 unit project
in Kelowna is developed and marketed by Cove Properties Ltd.
under the name
Playa del Sol. "The Giusti Group has provided
prompt, professional and outstanding service to our company for many
years. Giusti's attention to maximizing efficiency through the use
of state-of-the-art equipment and formwork has been exemplary. Joe
[Giusti] and his team continue to impress us with their
unwavering dedication to improving their craft", confirmed Grant
Klapstein, President,
Cove
Properties Ltd.
|
|
Geotechnical Complexity
The building site was complex geotechnically for
two reasons: first the danger of liquefaction under seismic
conditions; and second, settlement under static loads.
"To eliminate the possibility of liquefaction,
we used vibral compaction and sand columns", said Randy Hillaby,
geotechnical engineer with
Levelton. "And
we preloaded the site to prevent static settlement."
As the site was close to Kelowna Lake, with its
high water table, dewatering was required to keep the excavation
open and relatively dry. |
|
 |
|
The building site required
complex geotechnical remediation work |
|
|
Structural Engineering
As the remediated soils could only support loads
of 2,000 pounds per square foot, large footing pads were required to
transfer the loads of the building into the ground.
"Our largest pad measured over 15' square, with
a depth of 30 inches", said Brian Tomecek, Structural Engineer with
TRL & Associates Ltd.
"Typical steel configuration was 25 to 30 mm at 300 mm on center." |
|
 |
|
Typical pad reinforcing was 300 mm on center |
|
|
Footing Layout
The irregular building site made form layout very difficult. "We
decided right from the get-go to use a robotic total station",
said Scott Saunders, Project Manager. "Laying out 270 pads on
different angles using strings would have been a nightmare. With the
station, one man does the layout - a huge labor saving!"
|
|
 |
|
Cam Mitchel uses the
robotic total station to check form location |
|
|
Setting the screeds
2x10s were precut to the required pad
dimensions, and hinged at each corner for fast installation and
stripping.
Three 2x4 stakes were driven along each 2x10, and a laser used to
locate the exact height. |
|
 |
|
Screed
board height was accurately
determined using a laser |
|
|
Installing Fastfoot®
62" fabric width was used to form the deeper pads. "It is essential
to provide adequate slack in the fabric", said Scott. "Otherwise
there will be too much downward pressure, leading to form failure."
Bricks are used to hold the fabric in position prior to installing the
steel reinforcing.
Note the dewatering pipe in the bottom left corner. |
|
 |
|
Fastfoot® standard fabric was
used to form the 30" deep pads |
|
|
Bracing was installed on each stake
to withstand the significant lateral loads. |
|
 |
|
Travis
Patrick installs bracing to
withstand the significant lateral loads. |
|
|
Reinforcing Steel
25 to 30 mm rebar was used throughout the footings, with horizontals spaced
300 mm on center. |
|
 |
|
An overhead crane was used to
install the heavy steel reinforcing grids. |
|
|
Concrete
Concrete was supplied by
Burnco Concrete,
with branches throughout Alberta, and recently expanded into BC in
Kelowna, Penticton and Burnaby. 32 MPA concrete was supplied for the
footings and slabs.
"This project used a lot of concrete - over 13,000
yards", exclaimed Brandon Moffat, sales representative for Burnco in
Kelowna. "Fastfoot® is an excellent form as it ensures proper
hydration of our concrete on dry sand and clays during the summer." |
|
 |
|
Cam Mitchel places over 30 cubic yards
of concrete in this single pad |
|
|
The concrete was placed in the deeper pads in
two lifts. "From our experience, any pad deeper than 24" is best
poured in two lifts", said Scott. |
|
 |
|
Tyler
Toulous vibrates the second lift of
concrete |
|
|
Stripping
Removing the stakes and screed boards is
simple with Fastfoot® as there is no contact between the lumber
and the concrete. |
|
 |
|
Stripping is fast and easy with
Fastfoot® |
|
|
Site Logistics
Towards the end of the project, it becomes
increasingly difficult to store and move formwork. "One of the real
advantages of Fastfoot® on this tight site is the reduction of forming materials required",
said Scott. |
|
 |
|
As the project completes, there
is less and less room available for form storage |
|
|
Fastfoot® Performance
"With the bag, labor minimized. Hence more
efficient. And the job gets done", confirmed Scott. |
|
 |
|
"Labor
minimized... and the job gets done." |
|