|
AVANTE
CONSTRUCTION POURS FASTFOOT® RECORD - 1,330 YARDS OF CONCRETE
Avante Construction Ltd. of Surrey
BC is forming and pouring the foundation and concrete structure for a three story
tilt-up commercial project at 13888 Wireless Way,
Richmond, BC.
Since 1972 Avante Construction
has been building concrete structures throughout the Lower Mainland, BC. "We did our first tilt in
'87", said
Fil Jorge,
President. "We have used Fastfoot® on the last three
tilt-ups. It's a real money saver."
|
|
The Project
|
 |
|
This
impressive three
story tilt-up office building was designed by Bunting Coady
Architects for PK Projects Ltd. |
Bunting Coady
Architects designed the 116,000 square foot building for developer
PK Projects
Ltd. of Richmond, BC. "Our clients are in the
software industry and building appearance is extremely important", said
Rick Bos, Project Manager for
Phase V of 'Commerce Court'.
General contractor for the project
is Westcron
Construction Ltd. of Richmond, BC. "Westcron has been constructing
commercial tilt-ups for over twenty years", said
Gary Jackson, Site
Superintendent.
|
|
Geotechnical Conditions
"The ground conditions for the site consist
of firm clayey silt over saturated sand”, said
Nigel Denby,
Geotechnical Engineer with
Jacques Whitford. "About two meters of permanent fill was
imported onto the site to raise the building above the flood plain.
Temporary fill (preload) was brought in to compress the clayey silt
crust, prior to constructing the building."
"As the building is relatively light, during
an earthquake, the foundations for the building are designed to
'float' on the clayey silt crust. Therefore, even if the saturated
sands liquefy during an earthquake, the crust itself will support
the building load," said Nigel.
|
|
 |
|
Fastfoot® has been stapled in
position in a typical column footing measuring 18' x 18' x
28" deep. |
|
|
Structural Engineering
The building structure consists of exterior tilt-up
walls and interior steel columns. Floors are steel
decking topped with concrete.
As the design capacity of the soil is only 1,500 pounds per square foot, large footing pads
are required to
transfer the building loads, and ensure the
footings don't puncture the clay crust.
"Our largest pad was over 60 feet by 60
feet and 3 feet deep to distribute building loads over the clay
crust", said Renato Camporese, Structural Engineer with
Read Jones
Cristophersen |
|
 |
|
Les Silva
places concrete and Wes Wiebe checks height in the center of
a large pad supporting a central staircase. |
|
|
Installing Fastfoot®
2x4 stakes were driven around the
perimeter of the pads, and 2x8 screed boards attached at the correct height
using
a laser level. "We used
37" Fastfoot® for most of our pads and footings",
said Wes Wiebe, Cribbing Foreman. "We attached the fabric to the top of the
screed boards with a hammer
tacker and 3/8" staples." |
|
 |
|
15 ready
mix trucks were required to fill this 40' square pad formed
with Fastfoot®. |
|
|
Comparing Fastfoot® to Plywood
Bulkheads
"There are three very big advantages using Fastfoot®", said Wes. "First,
less labor. With plywood, you construct 2x4
frames to support the plywood. Not only do these take time to
build, but they are heavy to lift. With Fastfoot®, we drive our
stakes, set up screed boards, and staple fabric. Finished!"
"Second, with Fastfoot®, you attach your screed board to the
finished height of the footing.
This
makes it real easy to fill and screed your concrete. With
plywood, you have to mark the height on the inside of the form and
fill and screed to this height. Much more difficult." |
|
 |
|
This
plywood form gave way at the base. Quick work by Avante
allowed the form filling to be completed. |
|
|
"Third, stripping with Fastfoot®
is fast and easy because the fabric prevents the concrete from
contacting the lumber. Removing stakes and pulling off screed boards
takes seconds. The fabric stays."
"With plywood bulkheads, each section weighs over 150 pounds,
and labor costs are huge to move these around. Fastfoot®
weights only a couple of pounds!" |
|
 |
|
This
plywood form is being backfilled at the base to prevent form
failure - but installation and stripping costs increase
dramatically. |
|
|
Reinforcing Steel
"Typical steel configuration is 20 to 25 mm rebar (#6 to
#8) throughout the footings, with horizontals spaced
300 mm on center", said Renato Camporese, Structural
Engineer. |
|
 |
|
This large
pad will support the central elevator shaft and measures 65'
square. Steel is #8 spaced on 10" centers. |
|
|
Placing Concrete
Concrete was supplied by
RMC Ready-Mix
Ltd., Lower Mainland BC. 32 MPA concrete was supplied for the
footings and slabs.
"This project used a lot of concrete. Over 1,330
yards in the footings alone", exclaimed
Rolly Enarson, sales
representative with RMC. "Fastfoot® is a winner for projects
like this - it eliminates forming plywood!" |
|
 |
|
A typical
footing pad for an interior steel column. |
|
|
Screeding the Concrete
With Fastfoot®, the screed boards are set at the top of the footing,
making concrete placement and screeding simple.
Click here to view a
short video.
In deeper pads, concrete was placed in
two lifts. "Any pad deeper than 24" is poured in two lifts",
stated Wes. |
|
 |
|
Screeding
the concrete is easy with Fastfoot®. |
|
|
Perimeter Footings
Complex footings around the perimeter of this building are easily
formed with Fastfoot® as only stakes and the screed board are
required. Fastfoot® is quickly stapled to the top of the screed
board, adjusting automatically to footing
height.
Click here for a
video pan of perimeter footings. |
|
 |
|
Complex
footings are quickly formed with Fastfoot® |
|
|
Concrete has been placed in the perimeter
footings. Stripping is fast and easy as no concrete contacts
the stakes or screed boards. |
|
 |
|
Complex
perimeter footings filled with concrete |
|
|
Avante Employee Training
Avante requires all new employees to complete
their training program by installing column hardware using the
'Jimmy
Hoffa' method.
Click here for details. |
|
 |
|
Darrell
does the 'Jimmy Hoffa' to complete his Avante training
program. |
|
|
Fastfoot® Performance
"Fastfoot® is great. It minimizes labor
and materials. We get out of the ground faster," enthused Wes
Wiebe, Cribbing Foreman for Avante. |
|
 |
|
"Fastfoot®
does it better!"
confirmed Wes Wiebe, Cribbing Foreman for Avante. |
|